Element 2 - St. David's Drive, Airdrie, ML6 9QR

Work here began on Monday, 14 September and is expected to last approximately 10 weeks.

Around 81 metres of new 900mm diameter storage pipe and five new manholes will be installed as part of this element of the project. The work will take place in a grassy area beside a public access path near homes on St David’s Drive.

To allow the work to be carried out safely, the rough path leading to the wooded area will be temporarily unavailable during construction. Machinery and vehicles will be kept within the site compound to help minimise traffic on surrounding roads and reduce disruption to the local community.

Work will also take place on Saturdays to help expedite progress.

Once the work is complete, the site will be fully reinstated and returned to its original condition.