Spindlehowe Road Uddingston

Project Overview
We are delivering a package of investment to improve and protect the water environment in Uddingston.
Part of our £500million Improving Urban Waters programme, we are delivering a significant upgrade of the wastewater network in the town.
At a Glance
- Multi-million pound investment
- Delivered by Caledonia Water Alliance
- Work to begin in October 2026
Protecting the environment
The project will help to help manage heavy rainfall, protect the community from flooding and improve the water environment
What We Are Doing
We will be constructing a wastewater storage tank, chamber, headwall, kiosks and associated infrastructure in land west of Spindlehowe Road.
Work will begin on Monday 26 October 26 for approximately 11 months.
In order to ensure the safety of the public and our operatives during this time, Spindlehowe Road will be closed to vehicles south of the junction with New Edinburgh Road with no parking permitted. A section of footpath will also be closed with a diversion route in place to maintain pedestrian access.
Unfortunately, the removal of trees is required to facilitate the safe delivery of the works and future maintenance of the chamber. Tree clearance will commence on Monday 12 October for five days, during which time Spindlehowe Road will remain open.
Why We Are Doing It
As part of the current investment period, Scottish Water is working to improve urban waters in support of Scotland’s River Basin Management Plan (RBMP). RBMP aims to improve water quality in several river basins across Scotland.
These upgrades have been designed to help manage heavy rainfall, protect the community from flooding and improve the water environment.