River Laggan mains renewal

Project Overview
We are replacing the water main along the B8016 to ensure residents continue to enjoy clear, fresh drinking water.
Work is planned to begin in early March 2026 and the work is expected to last three months.
Throughout the works, the B8016 will remain closed at a section near Laggan Bridge. Diversion routes will be in place. Information on this can be found in the pictures below.
At a Glance
- Work will start in March 2026
- Duration of works: Three months
- B8016 closed for duration of works
- Delivered by our partner - Morrison Construction
During the works, temporary parking restrictions will be in place on Shore Street, Bowmore to allow the safe passage of cars in both directions.
Works will be completed by our partner, Morrison Construction.
Works will be completed by our partner, Morrison Construction.
B8016 Road closure
Image shows where the road will be closed
Parking restrictions
A graphic showing the separate areas that will be under parking restriction during the three month project.